Footing
Starting Course
Steel Reinforcing &Rebar
Thermalite Course Placement
Corners & Lag Screws
Windows & Doors
Electrical & Plumbing
Metal Bracing
Concrete Core Pouring & Leveling
With Scaffolding in place, the concrete should be poured at a 4” to 6” slump with a 1/2” or - aggregate placed in a maximum lift of 4’ per hour. Vibrate around windows and doors with a pencil vibrator. Once poured, trowel-level the concrete pour, check for height, install and level the j-bolts accordingly.